Clean Water Center
← All Projects
Clean Water Center and Perimeter Wall combined Bid Package
Near Actual Project Rendering 1
Status: Out for bid
Closing Bid Date: November 11, 2026
Estimated Construction Cost: $68.5M
Project Goal: To replace the functionalities of the existing Maintenance Building, Administration Building, Laboratory/Control Building, and Compliance Inspection Building with a new Clean Water Center complex, to be located on the north side of Carl Road at the entrance to the City's Water Pollution Control Plant (WPCP).
Additional employee/visitor parking, site lighting, road improvements, and security enhancements at the Plant’s main entrance are also included in this project.
Near Actual Project Rendering 2
Project/Construction information: The major project elements for the Clean Water Center include the design and construction of a two-story building to house multiple functions, including administration office functions; laboratory, operations, and staff support; maintenance and instrumentation shops; electrical room, maintenance office, warehouse and storage areas; and meeting rooms for public outreach. The project also consists of civil and sitework improvements, including completion of the new perimeter wall, landscaping, paving and striping, staff and visitor parking, and lighting in the parking area and along Carl Road. The Clean Water Center will meet U.S. Green Building Council LEED Gold rating requirements.
Demolition of the existing Administration Building and construction of additional temporary office trailers for plant staff are also included in this project scope.
The project additionally includes improvements to the Recycle Yard and Carol Road. The Recycle Yard is located on the south side of Carl Road and adjacent to Recycle Hill, one of the City’s closed landfills. The major elements for these improvements include:
Recycle Yard Improvements – Adding a new paved employee and visitor parking lot with an ADA accessible route to the WPCP, Clean Water Center and EV parking stalls. Residual municipal waste materials are present beneath the Recycle Yard (placed during landfilling operations at Recycle Hill). Because of the presence of the residual waste materials, paving of Recycle Yard must comply with the requirements to be defined by the Local Enforcement Agency (LEA) and the Regional Water Quality Control Board (Water Board), who share regulatory oversight responsibility for Recycle Hill.
Carl Road Improvements – Installing security fencing and an electronic security gate at the entrance to the WPCP facility, as well as installing lighting at the Recycle Yard and along Carl Road.
While the future western portion of the Perimeter Wall is shown on the Clean Water Center drawings, the Perimeter Wall is covered in its own design package that will be bid along with the Clean Water Center.
Near Actual Project Rendering 3
Perimeter Wall
Perimeter Wall Plan View
Project Goal: This project will complete the flood protection system that is needed to keep the Plant dry during 99% of coastal floods.
West Perimeter Wall Details
Project/Construction information: This project will construct the new western portion of the Plant perimeter wall and security fencing. This package includes around 2,300 linear feet of retaining wall with engineered wall foundation that will connect to the recently built eastern Perimeter Wall to provide a comprehensive flood protection system and groundwater seepage protection around the WPCP. It also includes utility relocations and new sidewalks and ramps for rerouting public access of the Bay Trail during construction of the western and northern portions of the wall.