Navigation

Projects, Milestones, Timing

The relatively small size of the main plant area and the need to maintain continuous operations 24 hours per day, seven days per week, largely determines the phasing of the Sunnyvale Clean Water Program implementation. Some existing facilities must be decommissioned and demolished to create space for construction of new facilities, and no more than two large contractors can work on the site simultaneously. Other factors that determine the overall proposed schedule include cost, the timing of future regulations (such as new discharge requirements for nutrient removal), and projected increases in flows and loads.

Figure 1

This aerial depicts construction activities at the Plant through the end of 2017. Click on the image for the full version.